Hi all
my team had a retrospective today, the issue is that they often drag issues from To-Do lane to In-progress lane without looking at the Review lane.
So they have this question:
- Is it possible to have a blocker to drag issues into ToDo if there are amount X in the review lane? So they have to clear the review lane before they take on new tasks?
I've looked into the automation rules, but I couldn't find any solutions there.
Does anyone have some solutions?
best regard
Mikel
Hi Mikel,
You might be able to do that by placing a custom validator on the transitions using JMWE or ScriptRunner.