Hi Team,

I need to make assignee as unassigned after the issue has moved from project A to project B. I need when issue gets moved to Project B, the assignee should automatically become unassigned.

I have a scenario where the user has Assignable User permission in Project B also, so it is not possible to unassign it directly.

I am also using Script Runner Plugin.

 

Kindly help if any script can be written or any other can be followed to achieve this.

 

1 answer

1 vote
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 11, 2015

You'll need to write a "listener" that listens for "issue moved" events and updates the moved issue with a blank assignee (the script runner can do this)