Preventing Issues advancing to Done if sub-task not complete Edited

How do you prevent an Issue advancing to Done if the sub-task isn't Done? Note that I've also made the sub-task a blocker of the main Issue.

3 answers

1 vote

Hi @Ed Green,

I think the workflow-condition "Sub-Task Blocking Condition" is there out of the box.

Add this condition to the workflow steps, which are leading to the status "Done".

If there are open subtasks then, you won't see the closing transition of the parent issue.

0 votes
Alexey Matveev Community Champion Dec 08, 2017

Hello,

You can not make it out of the box. You would need an addon. For example, if you have Adaptivist ScriptRunner, then you can use "All sub-tasks must be resolved" condition. You can read more here

https://scriptrunner.adaptavist.com/latest/jira/builtin-scripts.html#_all_sub_tasks_must_be_resolved

Hey @Ed Green,

One other option for doing this is to use the Power Scripts add-on.

Here's a step-by-step guide on how to prevent an issue from closing unless all sub-tasks are closed.

Hope this helps!

Johnson

Suggest an answer

Log in or Sign up to answer
Community showcase
Published yesterday in Jira Service Desk

Frequently Asked Questions for Jira Service Desk (AKA JSD FAQ)

Just the FAQs! Welcome to the Community, and this Focused-FAQ! Here, we've pulled together some of the most frequently asked questions associated with Jira Service Desk (JSD). We hope ...

85 views 0 8
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you