Hi All,
As Product Discovery matures into a shipping product, it would be good to see roadmap view (like in Advanced Roadmaps/Project roadmap) and the true nested hierarchy features release (as are discussed in other questions on this thread). We currently utilize another product (Aha) for some of these features, but would like to consolidate into the Atlassian ecosystem.
Is there a "roadmap" for the beta of the product to be able to understand the features that are planned, and relative timeframes? Also, are there plans for importing roadmaps from other projects, or at a reverse sync from Jira to populate a Product Discovery project?
Thank you
@Lindley Tam we'd need more information on what tickets you've added as delivery tickets to answer this, but 274 is 2 x 137 so have you added the tickets twice, e.g. adding the epic and then adding each ticket individually as well?
Good catch @Stephen_Lugton that was the feedback from the JPD engineering team as well - if you add them twice they're going to be counted twice
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks @Stephen_Lugton ! I'm afraid I don't really understand what you mean by adding each ticket individually. What we do is we either use the "Create a delivery ticket" action (so that a new empty epic is created, and then we create individual tickets in Jira itself under that epic created), or we link an existing epic.
I don't really see anywhere we could've added them twice because the epic linked clearly shows just one ticket for each task unless I am not using JPD as intended.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Could you please send a screenshot that includes the whole screen (tcrusson@atlassian.com) - I'd like to check what's going on. Thank you!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Lindley Tam we just looked at your screenshot: is it possible that you've added a value for the storypoint field in the epic?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Tanguy Crusson thanks so much - i think that was the issue. There was an automation that was done by a previous delivery manager that automatically summed the story points in the epic, and that would be reflected in the 'Story Points' field. I removed the summed values from that field and the delivery progress works as expected now.
Thank you again for taking the time to look into this!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.