Is it possible to link events in a team's calendar?

Max December 21, 2017

Hello All,

I'm wondering if there is any option to link events in MS Project-like style to clearly state dependencies between the events/tasks? Assuming I have a bunch of events planned for upcoming months, all related (tentative sprint plan with scrum rituals). If I had to shift it all to the right how would I do that? Editing manually multiple events is not very convenient. 

1 answer

1 accepted

0 votes
Answer accepted
Shannon S
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
December 22, 2017

Hi Maxim,

I believe you're referring to this feature request that was logged previously for Team Calendar?

Unfortunately it is indeed not possible and it's not a feature we plan to include in the near future.

Let us know if you have any questions about this.

Regards,

Shannon

Max December 24, 2017

Hello Shannon, 

Thank you for your reply. Yes, this was exactly what I wanted to ask. Well noted that this request has a very low priority and doesn't have a chance to be implemented in the nearest feature.