Using the information here: https://confluence.atlassian.com/doc/chart-macro-163415075.html
I created the attached gnatt chart.
I keep getting "Requires end >= start." if the dates are in the same year. A year out it works, but the date headings are nonsense.
Many, many, many thanks in advance.
Edit the Gantt chart settings Date to reflect capital letters for month - MM/dd/yyyy. This resolved the error for me.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
As a workatound you can try Chart from Table Gantt chart if you have Table Filter and Charts add-on installed.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I don't have the permissions to download any add-ons and the admis aren't likely to pay for it. Any idea how to get the out-of-the-box gnatt chart macro working as illustrated? Using Atlassian's documenation it doesn't render as expected (unusable). Any input is aprreciated!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.