Using the information here: https://confluence.atlassian.com/doc/chart-macro-163415075.html
I created the attached gnatt chart.
I keep getting "Requires end >= start." if the dates are in the same year. A year out it works, but the date headings are nonsense.
Many, many, many thanks in advance.
Edit the Gantt chart settings Date to reflect capital letters for month - MM/dd/yyyy. This resolved the error for me.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
As a workatound you can try Chart from Table Gantt chart if you have Table Filter and Charts add-on installed.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I don't have the permissions to download any add-ons and the admis aren't likely to pay for it. Any idea how to get the out-of-the-box gnatt chart macro working as illustrated? Using Atlassian's documenation it doesn't render as expected (unusable). Any input is aprreciated!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.