R-Date | Target Date (Tentative) | Activity |
---|---|---|
PAC-4 | <DD-MMM-YYYY> | Project Team Review (Phase 2 team approval) |
PAC-3 | <DD-MMM-YYYY> | Desk Review with Product Operations |
PAC-0 | <DD-MMM-YYYY> | Pre-PAC Review
|
Hey guys,
Here is my usecase:
I want to use the table transformer macro in confluence to automatically calculate dates for PAC-3 and PAC-4 based on PAC-0 date that I would manually provide.
Ex: I'll mention PAC-0 date as 20-May-22 and I want PAC-3 to automatically calculate 17-May-22 and PAC-4 date as 16-May-22. I'm getting an error in the SQL query. Can someone help pls?
Hi @sindhushandilyaa ,
We assumed that the number after your PAC- is a number of days to subtract from the PAC-0. So our developers came up with the following solution:
Don't forget to set the correspondent date format:
And use the following SQL query:
SELECT T1.*, FORMATDATE(ADDDATE(TT1.'Base', INTERVAL T1.'R-Date'.split("PAC")->1 DAY)) AS 'Target Date (Tentative)' FROM T1, (SELECT 'Target Date (Tentative)' AS 'Base' FROM T1 WHERE 'R-Date'="PAC-0") AS TT1
Hope this helps your case.
Hi everyone, We’re always looking at how to improve Confluence and customer feedback plays an important role in making sure we're investing in the areas that will bring the most value to the most c...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.