You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
Hi there,
we are currently preparing to replace the current "ui clicked" Build and Deployment Plans by bamboo specs plans.
We are currently testing an finalizing the spec files.
I'm wondering how, I can later "replace" the "clicked" plans, by the new plans to keeping especially the Build Number, because the number is part of the release naming startegy.
So, do I just have replace the "names" and "keys" on the specs file to match the old keys of the UI plans?
Thanks
Joerg
Yes, if you use existing plan key at specs, it will be switched to UI-readonly mode
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.