Rerun a part of a completed build.

Jothi December 1, 2017

Hi,

I'm new to bamboo.

I have configured a single plan with 3 different stages where second 2 stages are manual stage.

When I'm trying to rerun the particular stage say stage 3, it requires to run previous stage say stage 2 also.

Seems I'm facing this case only in after successful run of stage 3.

When failure of stage 3 , I can able to rerun stage 3 alone.

but I need to rerun stage 3 alone after successful run too

Can anyone help me on this?

1 answer

1 vote
Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 2, 2017

It is not possible. You can check https://jira.atlassian.com/browse/BAM-9611 for some context. Also, check the last comment about deployment projects.

Jothi December 4, 2017

Ok.thanks