I am new to JIRA Automations and have created a rule that initially schedules the creation of a Task. Following this, a Sub-task is supposed to be created and linked to its parent Task. While everything else works as intended, I'm encountering difficulties in the final step of linking the Sub-task to the Task within the same automation rule.
Hi, @Marija Akmacic
Welcome to Atlassian Community.
To link subtask to parent task, created by rule, you need to make a branch in rule, and select there "Most recently created issue"
Thank you!