Time Tracking in Greenhopper

Phil Lancaster
Contributor
February 28, 2013

I am estimating in story points and time tracking in hours. I want the remaining hours field in the user story to be the total of the remaining hours in the sub-tasks. But I cannot enter sub-task remaining hours in Plan mode, only in Work mode. The user story is not available in Work mode until I start the sprint. But if I start the sprint without remaining hours in the user stories, the ideal burn-down chart is not plotted.

It's a Catch-22 situation. The only way I can get the initial burn-down plotted is to put guesswork hours remaining nto the user stories, whereas they should be the sum of the sub-task hours remaining. But I can't enter the sub-tasks hours remaining until I've started the sprint.

Surely I should be able to enter sub-task hours remaining in Plan mode?

Jira 5.2.5 Greenhopper 6.1.2

2 answers

1 accepted

Suggest an answer

Log in or Sign up to answer
1 vote
Answer accepted
Dobroslawa Wierzbicka
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 21, 2013

You cannot edit the Sub-tasks' remaining estimates directly in the Plan mode, but you should be able to edit the field in the Sub-task's Edit Screen (click Actions > Edit in the Sub-tasks section of the Story's detail pane). Would that be a suitable workaround for you?

Tom Wilhelm March 24, 2013

I can't speak for the original poster, but given the workflow we're talking about, it's an inefficient workaround at best.

My team have basically 2 hours for our Sprint Planning meeting every two weeks and we have to get through a lot of stories... selecting which stories to include, then breaking down with sub-tasks how we'll approach each one. With an average of 30-35 stories, half of which need to be broken down into 2-5 sub-tasks each, I figure there are ~50 or so times we need to enter a sub-task remaining estimate during the 60-75 minutes we have left after agreeing on the sprint contents.

You can see how the inefficiency can multiply quickly when its core to the workflow...

Maybe there's just a better way to organize our workflow that aligns with the software design?

0 votes
Tom Wilhelm March 21, 2013

I asked the very same question on the Configurating Estimation and Tracking page and would love to hear an answer on this!

TAGS
loom essentials certification, loom training, get certified in loom, atlassian certification, loom async video, video messaging skills, atlassian learning, loom for teams, online certification, loom badge, loom for business, atlassian education

Get Certified in Loom! 🧑‍🎓

Time to up your Loom game! The new Loom Essentials Certification is here! Show off your skills, learn pro tips, and get officially recognized. Perfect for taking your video messaging to the next level.

Learn more
AUG Leaders

Atlassian Community Events