Structure plugin - how to import from another structure

Santhosh R Bhat
Contributor
March 23, 2024

Hello,

We are using Jira cloud. Structure plugin. Lets take we have 5 projects. 

Project Managers of each project define a structure for 5 projects separately like below.

Epic -> Story -> Subtask. Progress% for each story is added. Overall progress is calculated at group level which gives the progress % of project. This structure lists all stories and subtasks in the project.

 

Now at Program level is it possible to create a structure which shows projects and their progress% only. We do not want to load all the stories and subtasks of all the 5 projects in the program level structure because it will be a huge number of list. But want only project level progress shown.

Project 1 30%

project2 50%

project 3 80%

.....

 

Please help on how to create it. 

If there is any other way to use formula to get this done, please share.

Thanks

 

 

2 answers

1 accepted

Suggest an answer

Log in or Sign up to answer
0 votes
Answer accepted
Stepan Kholodov _Tempo_
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
June 25, 2024

Hello @Santhosh R Bhat 

The Copy to Jira (known as Effectors on Server/Data Center) feature was just added to Structure Cloud. You can find out more about it on our Wiki. Now it's possible to first write the Progress column's values in a Jira field and then use it in another structure, if needed.

If you have any questions about it or Structure in general, please reach out to us directly at our support portal.

Best regards,
Stepan
Tempo (the Structure app vendor)

0 votes
Stepan Kholodov _Tempo_
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
June 13, 2024

Hello @Santhosh R Bhat 

It is only possible if you create a structure that contains issues from all other structures - this way the Progress will be calculated using the data from the structure. The Progress column creates a custom local value, which is not reflected in Jira; at this time, it is also not shareable between structures. We have plans to allow it in the future.

If you have other questions about Structure, please reach out to us at our support portal directly, and we'll get back to you shortly.

Best regards,
Stepan
Tempo (the Structure vendor)