We are currently starting to evaluate Easy Agile Programs. Unfortunately we have a lot of dependencies between Trains (Programs) that we would need to visualize.

According to the page https://updates.easyagile.com/announcements/external-dependencies-now-in-view they should be shown as black dependency lines, but I am only able to see them as the black link icon, which is not enough.

What part of the configuration in the programs am I missing, in order to visualize external dependencies?

1 answer

Suggest an answer

Log in or Sign up to answer
0 votes
Elizabeth Cranston [Easy Agile]
Contributor
January 9, 2025

Hi @Erik Schumann 

Thanks for reaching out and sharing your challenges around visualising dependencies across trains.

I'm Elizabeth, the Product Manager for Easy Agile Programs. We'd love to chat to you about your needs. I will share a link to my calendar via the support request you have raised with our team.

The black lines for external dependencies have now been evolved into an icon on the issue card. When clicking this icon you can see the details of the external dependency. Keen to understand what else you need to improve the experience for your teams.

In the meantime, here's a link to our documentation on how dependencies can be managed in Easy Agile Programs. 

Have a great day and I look forward to catching soon

Thanks Elizabeth