After completing my current sprint even all the issues in the done status(which is the last column in workflow) are getting spilled over to next sprint. Weird thing is while closing sprint it's showing all issues are completed but after closing all the issues are marked as incomplete issues.
Hi @Roopesh Palukuri ! I would also agree with @John Funk on his responses, but just out of curiosity, I was wondering what Status Category that your QA Passed status is in on your board. If QA Passed is still in the In Progress Status Category, that might cause the result your experiencing. I don't know - just curious what is happening. :)
Hi Roopesh - Welcome to the Atlassian Community!
Is there some type in the status of the issue in the History of the issue?
And does it happen to all issues in the Sprint? Or just a few? And do the issues have any sub-tasks?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hey @John Funk thanks for taking time to answer , there are linked test cases to the stories and for test cases QA Passed is the last status. And we're making sure they are put in QA Passed status. I think test cases are the culprits here as after finishing sprint when I check the sprint report test cases status is showing as QA in progress but when I open up that particular test case status is showing as QA Passed. And yeah it's happening from last 4 sprints.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Are you using a particular test app?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
X ray we're using for testcases, but the thing is we have other boards but for those boards this issue is not happening. Those are pure scrum boards. But for this particular board for which this issue happening it's Scrum and Kanban mix.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
you should probably contact the vendor then for support.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Welcome to the community.
The Done status also need to be in the final column of your Sprint board, otherwise it's no considered burned and will be transferred to the next Sprint
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hey @Marc - Devoteam - The question states that the status is in the last column of the board.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.