Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in

Next challenges

Recent achievements

  • Global
  • Personal

Recognition

  • Give kudos
  • Received
  • Given

Leaderboard

  • Global

Trophy case

Kudos (beta program)

Kudos logo

You've been invited into the Kudos (beta program) private group. Chat with others in the program, or give feedback to Atlassian.

View group

It's not the same without you

Join the community to find out what other Atlassian users are discussing, debating and creating.

Atlassian Community Hero Image Collage

Huge kanban release (650 tasks) fails

Hi!

We are switching from scrum to kanban.

Now, unfortunately, all tasks we have finished before, show up as unreleased in the kanban board.

Just clicking "Release..." fails with a timeout.

Is there anything we can do to pack those tasks away from the kanban board and mark them as released?

4 answers

What version of JIRA are you using, what version of Agile are you using? What kind of time out? can you attach the timeout error? If it is fronted by a webserver, the timeout could be there. 

Sorry for the delay, we got it solved using the issue navigator.

Hi Volker, how were you able to solve this using the issue navigator? I'm having the same issue.

Please help, same issue

I am experiencing the same issue, how were you able to use the issue navigator to resolve the time out release in kanban?

I'm having the same issue. Is there a solution or work-around?

Please update on how you were able to solve this. We are having the same issue.

Hi, I am also having this issue. We get a timeout error when I try to release the 600 tickets in the "done" column in our Kanban. I changed the version number after the popup said the version I wanted to use already existed, but the column did not update to make the "done" tickets go away on the board. We are using JIRA cloud and its version 6.5-OD-03-002.

 

I'm guessing I'm probably not doing something right so any help would be appreciated!

 

 

Screen Shot 2015-05-19 at 9.38.54 AM.png

I think the workaround which uses Issue Navigator is:

- Go to Issues > Search for Issues

- Search "project = ____ AND fixVersion is EMPTY AND resolution = Done"

- Tools > Bulk edit issue (You probably have a limit of 1000 issues at a time).

- Select the issues, Next.

- Edit issues.

- Change Fix Version/s field to the Release you want. 

- Scroll to the bottom and uncheck "Send mail for this update" and click Next.



This will do the same thing as "Releasing" off the Kanban board and avoid the time outs. It worked for me, I myself had 2150 issues to release off a single Kanban board and used this workaround.

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Agile

On-demand: Fireside chat with Atlassian on scaling agile organizations

Scaling an agile organization and setting it up for success over the long term is a hard thing to do. We hear a common set of questions from customers all the time, questions like: Can agile scal...

3,946 views 2 17
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you