Every now and then, the question pops up, why does atlassian invites to use subtasks, but they dont show in the Burndown chart.
The answer is: no, that does not work. Some people help themselves with add ons and twisting and configuring them, that it somehow works out.
But until now, Atlassian did not provide a simple solution to that simple demand.
However, my personal solution is, that I reorganize my projects and boards in a way, that a story/task is the lowest level in my boards. As they are shown in all charts when closed, they need to be refined as much as possible, to have a chance to be set to done in one single sprint.
Enjoy!
It is important to understand what Atlassian is doing with Jira Software. It supports Scrum and Kanban, of course.
But the implementation of sub-tasks is a bit of a hangover from the original "scrum" process (and totally accurate for Kanban) whilst trying to not to annoy people doing Waterfall.
Sub-tasks are not sprint items, they are a fragment of a sprint item. So you should not "burn down" on them. Burn down is for sprint items.
Recommended Learning For You
Level up your skills with Atlassian learning
Learning Path
Apply agile practices
Transform how you manage your work with agile practices, including kanban and scrum frameworks.
Learning Path
Configure agile boards for Jira projects
Learn how to create and configure agile Jira boards so you can plan, prioritize, and estimate upcoming work.
Jira Essentials with Agile Mindset
Suitable for beginners, this live instructor-led full-day course will set up your whole team to understand how to use Jira with an agile methodology.