Hi,
i have couple stories that i defined in my scrum board and some of them need to be more than 2 weeks ( duration of one sprint) so i want it to be reflected in the portfolio as long duration but in current situation , it doesn't show duration longer then 1 sprint.
how can i modify it?
thanks
Amit
This might be an opportunity for your team to:
- break up that story into several smaller stories
and/or
- create an epic, split up the story into several smaller stories, and associate them with the epic.
Conceptually, a story should be "small enough" that it can be completed within one iteration.