I am trying to include an Epic in the Jira Portfolio. It is closed less than a month ago and even though I set "completed days" to 180, still the epic does not appear in the roadmap.

The epic appears in the filter, but not in the portfolio.
I tried and reopened the epic, it appeared in the portfolio!

Completed days (Issue sources).PNGJira Filter.PNGJira Portfolio.PNGPortfolio source scope.PNG

 

 

 

1 answer

0 votes
Joseph Chung Yin
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
October 8, 2020

@Incognito AM - What is your EPIC Status (NOTE this is not the WF Status of the issue) for TPMMAN-1458?  If the EPIC Status is set to DONE where your user has mark this EPIC as DONE in his/her board, then it will not show up in your AR plan.

In other case, if the EPIC above was already "CLOSED", then you build your plan afterward, then it will also not show up in the AR plan. 

Hope this helps.

Best, Joseph Chung Yin