Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in

evaluating jira including portfolio: some questions

drB July 12, 2018

 Hello,

 

I am evaluating jira and portfolio for a project. I created some releases, epics, user stories and added some levels in the portfolio hierarchy.

Questions and hope you can help:

1) How do I change the time bar from dates to e.g. sprints or releases in the plan?
Answer: set the filter to user stories will show the sprint. Would be good if it could be manually selected.

2) I added a few extra levels in the portfolio hierarchy though when looking at the portfolio plan, the plan can only show for one level (by selecting the button on the top left and set your hierarchy) is it possible to display multiple levels in the plan? E.g. Themes and epics?

3) Do I understand it correctly that the plan creation is done on the estimates and not by assigning it to a sprint? For example, I will have a large number of epics. Do I need to set the estimates for all epics or can we just assign them to a sprint for planning purposes?

4) in the configuration I have set the scheduling to base on target dates.
Though in the plan, the epics take the whole release and not only the sprint that they are assigned to

5) When adding my own level in the hierarchy, Epic cannot be chosen as an issue type. Why is this?

 

many thx. B.

1 answer

0 votes
Thomas
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
July 20, 2018

Hi @drB,

 

1 - It's possible to show the sprints for all hierarchy levels, there is an option to enable it in the schedule view configuration. You can read more about it here.

2 -  Currently the schedule view does not allow to see multiple hierarchies at the same time. There is a feature request you can comment and vote on here.

3 - For resolving dependencies, and doing capacity planning the estimations are needed, but issues can still show up in the schedule view without estimations if they have sprint or fixed release assignments or have Target dates.

4 - The scheduling priority order used for unestimated issues is Sprint > Release > Target dates

5 - The Sub-task, Story, and Epic level are Jira fixed hierarchies and Portfolio does not currently allow to change those. You can only add and modify hierarchy levels above epic.

 

Cheers,

The Portfolio for Jira Server team

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events