Working day configuration with Advance Roadmap new planning interface

Bhumika Dave December 28, 2020

Hello Experts,

How can I configure working days with New planning interface of Advance Roadmap?

Basically, I want to plan keeping holidays in mind, something like you can not start your ticket on 25th December or team will not work till 3rd January.

As a workaround, I switched to old interface, where the option is available, but still my Roadmap doesn't consider it after switching back to new interface.

Help appreciated!

 

Regards

1 answer

1 accepted

0 votes
Answer accepted
Ravi Sagar _Sparxsys_
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 28, 2020

Hi @Bhumika Dave 

Yes. Individual capacities and absence is not supported in the improved interface. You have to use the live plan which I know in comparison a bit more feature rich and demands far more time to get used it. 

Ravi

Bhumika Dave December 28, 2020

Thanks Ravi. Can you please elaborate on live plan? Is it Atlassian feature and how to use it?

Ravi Sagar _Sparxsys_
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 28, 2020

Hi @Bhumika Dave 

Yes live plan was the old version of Portfolio (now Advanced Roadmaps). If you want to learn more about the limitations of the improved interface then take a look at this page. In case you want to learn Advanced Roadmaps I made series of videos covering both live and improved interface in detail.

I hope it helps.

Ravi