Hello,
we are working Kanban-based with Roadmaps. If a developer is e.g. on vacation we reduce the weekly capacity accordingly but somehow Jira ignores it.
For example: Weekly capacity of the team is normally 40h (configured in the teams tab), the issue has an estimate of 50h & developer is absent in week 1 (= reduced capacity of 20h).
Expected behaviour would be that capacity is distributed with 20h in week 1 & 30h in week 2 but instead its distributed as if capacity had never been adjusted:
With the current behaviour capacity planning is not possible.
So, is there any way to change this?
Thanks in advance
If anyone else is interested in this issue, please vote for this feature request which adresses this: