Are you in the loop? Keep up with the latest by making sure you're subscribed to Community Announcements. Just click Watch and select Articles.

×
Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Why are adjusted weekly capacities not considered in capacity distribution?

Hello,

we are working Kanban-based with Roadmaps. If a developer is e.g. on vacation we reduce the weekly capacity accordingly but somehow Jira ignores it.

For example: Weekly capacity of the team is normally 40h (configured in the teams tab), the issue has an estimate of 50h & developer is absent in week 1 (= reduced capacity of 20h).

 

Expected behaviour would be that capacity is distributed with 20h in week 1 & 30h in week 2 but instead its distributed as if capacity had never been adjusted:RoadmapIssue.PNG

With the current behaviour capacity planning is not possible.

 

So, is there any way to change this?

 

Thanks in advance

 

1 answer

If anyone else is interested in this issue, please vote for this feature request which adresses this:

https://jira.atlassian.com/browse/JPOSERVER-3107