My Plan needs to support more than 5,000 issues. When will Atlassian increase support for more than 5,000 issues on a Plan?
Hi @Brian Boyle
We fully understand the need to be able to create larger plans and are actively working on being able to increase this limit across the board! At this stage I can't give any concrete timeline on when it'll be released unfortunately, but can definitely report that we're on it.
For the moment I would recommend reducing the scope of your plans or splitting them into multiple smaller plans. Voting on a JSWCLOUD ticket as Daniel Ebers has suggested is also a great way to signal your interest and get updates on the feature.
Cheers,
Daniel
Hi @Brian Boyle
I'd additionally suggest to watch & vote for the Suggestion:
Doing so you can signalize the Suggestion is important to your team. Same time you'll keep informed about it's progress.
Cheers,
Daniel
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
When it is ready.
Atlassian tend to only release features when they have got them ready.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.