Are you in the loop? Keep up with the latest by making sure you're subscribed to Community Announcements. Just click Watch and select Articles.

×
Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

What is the logic behind Estimates vs Capacity?

I really don't understand how I can use capacity functionality in Advanced Roadmaps as when I'm testing it ...it works opposite to what is logical for me. Im trying a way to escape from BigPicture Resource Planning as we don't find it user friendly, but...

Example:

  1. We put estimate (Original estimate) on the task 10h
  2. Estimate is not visible on the Plans (Resource management) in the column Estimates (h)
  3. I book time 1h in Tempo on that task
  4. Estimates (h) field in Plans now started to display value = 9h (it took out 1h from Our Original Estimate and put 9h into Estimate field of Plans)
  5. Capacity in Plans now just sees you need to work 9h while your capacity 100% is still full not affected by the fact I already used up 1h during that week. Only estimate decreased when you log time.

For me this behavior doesn't make sense.

I would expect that when I log time...my capacity decreases and not estimate Decreases to actually increase my capacity!!!

What Im doing wrong?

I would like to do following thing:
- put estimate on the task and display it in the Plans (ie. Original estimate field but can be something else) - estimate that wouldn't change automatically when I log time spent

- see what is remaining estimate after booking time in Tempo = Original estimate - time spent

- team capacity to be impacted the way, that estimated time is decreasing total Capacity

 

Thanks for your advice,

Anita

 

 

 

1 answer

0 votes
Daniel Ebers
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Jan 17, 2023

Hi @Anita Domańska

I found strong signs that "Original estimate" cannot be used within Advanced Roadmaps:

Also integration Tempo <-> Advanced Roadmaps seems to be something which is not supported:
https://ideas.tempo.io/ideas/T-I-938

In the first step I'd like you to ask to review the very first link if it corresponds with what you are observing. Happy to have some feedback here!

Thanks in advance!

Cheers,
Daniel