Are you in the loop? Keep up with the latest by making sure you're subscribed to Community Announcements. Just click Watch and select Articles.

×
Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Using advanced roadmaps to enter estimates

My team use Advanced Roadmaps with a plan configured for person-hours estimation.

When we enter the "Original Time Estimate" field in Jira's Issue View it automatically sets the Remaining Time Estimate to the value of the Original Time Estimate.

When we enter the "Estimate (h)" in Jira Advanced Roadmaps it only sets the "Remaining Time Estimate" an does not set the "Original Time Estimate".

Are we using it correctly? Can someone please explain how this works. From the looks of it initial estimates should be entered in the Jira Issue View and revised estimates should either be put in AR Estimate (h) field or Jira Issue View Remaining Time Estimate.

2 answers

1 accepted

1 vote
Answer accepted
Eddie Meardon
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
Dec 22, 2021

HI @Darrel Jackson

This is quite the doozy of a question.

While you can use either method to set the initial estimate for the issue, Jira (and Advanced Roadmaps) bases its project planning and estimation functions on the Remaining Time Estimate field: things like boards and sprint planning use this field and not the Original estimate field.

So in light of that, it makes sense that Advanced Roadmaps updates the Remaining time field as a plan in Advanced Roadmaps is meant to be a living, breathing thing that updates over the life of a project.

The original estimate field is a reference, but isn't necessary to a project. It's not necessary for project planning and if you don't want to update the Original estimate field, nothing says that you have to.

Does this help at all?

Cheers, 
Eddie

That’s a fair assessment. It would be nice to have the option though.

That is a correct assumption IF you enter the original estimate in the jira ticket.

What I would like to do is enter the original estimate via AR. Because I don't need to open every ticket separately. 
It would also be nice to use the same representation of the estimate. Now it show als 2h in the ticket and as 0,25 in AR. 