Can anyone help me with the following:

What field in Jira (Epics, Stories) maps to the capacity plan in Jira Plans using Kanban?

I can set-up a team as kanban, allocate tasks to the team. Set the Kanban capacity. The field "Estimates (d)" is used for allocating the workload to the kanban period in the planning.  But I can not find this field in the list of field configurations nor customfields in JIRA. 

What field do I need to use in the Jira ticket for a kanban board to make that the estimated workload in processed in the Jira Plan

1 answer

1 accepted

0 votes
Answer accepted
Daniel Capizzi
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
July 26, 2023

Hi @jeroen_wilmes 

When you're using days to estimate in your Plans that's reflected in the Time Tracking on your Jira Issue. That field will open a pop up where you can enter Time Spent and Time Remaining - it's the Time Remaining value which will show up in the Estimates field in your Plan.

Hope this helps! Please feel free to let me know if there's anything else I can help with here too.

Cheers,

Daniel

jeroen_wilmes
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 26, 2023

Hi Daniel,

 

Thanks a lot, that was exactly what I was searching for. It works as expected.

regards