Hello! I have an Advanced Roadmap plan configured to use Target start/end dates from sprint dates.
Sprint dates
Use sprint dates when issues don't have start and end dates
However the target dates don't totally line up with the actual sprint date
Start dates are the same but end dates are a day before. See screenshots
interesting.. thanks! I will take a look at your accepted answer! I already gave the incorrect completion date once today bc of this.