Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Target Start and Target End not updating for epics

I have an epic that has several estimated and unestimated stories.  When I auto schedule, it fills in target dates for everything as expected.  When I put estimates on the unestimated work, it correctly brings in the timeline for the newly estimated stories.  However, the parent epics target and end dates not updated based on the new information.

 

 

1 answer

0 votes
Rohan
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
Jun 20, 2019

Hi John,

Something to consider is that if your epic doesn't have an estimate, then the Auto-schedule will respect the start and end dates that were previously set. If child issues end up outside of the epic's start or end dates, then the epic will expand to include these new issues, but it will never shrink.

This is something we're currently working to improve.

Best Regards
The Portfolio for Jira Server team

Ok thanks.  As it stands right now I have to clear the target dates for all my epics before I use the auto schedule feature.