Target Date on Portfolio plan

GetConnected Atlassian Support November 26, 2018

Hi all,

I'm trying to add in my scope view target start and target end field but they disappear everytime I  make a calculate. 

In the target schedule I can't see my baseline. 

Did you ever had the same problem? 

1 answer

0 votes
Susete Alves Eccher
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 11, 2019

I think this happened when there is estimate, in which case the Portfolio does not consider the informed dates but recalculates.