Subtask of story with different assignee - how to do it?

Владимир Давыдов October 3, 2016

http://prntscr.com/cpgkt2 - when subtask is done by different memebers - how to assign them?

1 answer

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 3, 2016

You can't change the team of a subtask - the whole point of the Portfolio grouping there is that all tasks are done by the team.  But if you go to the sub-task, you'll find you can assign it to an individual.

Владимир Давыдов October 3, 2016

Yes, right. I can make assignment in Jira. But will Portfolio use this Jira-assignee in timing calculations?

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 3, 2016

My understanding is that the latest version will take account of that, yes.  (Older ones with the non-dynamic planning did not until quite a later version if I remember correctly)