Our company is converting to using a hierarchy level (top level being initiatives, middle epics, third stories). The previous system was epics, tasks, and subtasks. I'm tasked with converting the history of some of our tasks into this new system (previous epics become initiatives, previous tasks become epics, etc.).
Since some of these tasks are done and I'm wanting to show them on the advance roadmap, I'm confused as to why when I gave an epic stories that were already completed, only 1 showed while the rest didn't. I've refreshed and left the page multiple times, but they won't show in the roadmap.
^ Above it was it looks like in the roadmap view
^Above is showing WC-5 having more than one story under it
@Ciarra Anderson How long in the past were the non-showing stories closed? I think AR defaults the "Completed Issues" at 30 days, but you can change it to up to 999 I think.
This option is in the configuration settings in the "Issue Sources" section.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Good deal! You're welcome!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.