Are you in the loop? Keep up with the latest by making sure you're subscribed to Community Announcements. Just click Watch and select Articles.

×
Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Sprint Overstated

Hi, hoping someone can help with this query.

I have a team which is showing on JIRA Plans as having 118 story points assigned to the sprint. However when I view the sprint the team only has 80 points in the sprint.

 

Does anyone know how I can get the story points on the Plans view to be updated correctly?JIRA Blacklog Sprint.JPGJIRA Plans Sprint Capacity.JPG

2 answers

Hi @Kevin.Bruce 

The 38 points are on the Done issues. 
You should clear the Sprint field and/or fill the Resolution field as Done (not the status) on these issues (only possible during a status transition ! you'll have to modify the transition to Done with a post-action)

Watch out also "16 issues not assigned to sprint" probably means it will not be taken into account when you'll start the sprint.

Hope it'll helps !

thanks @Jean-Emmanuel BANQUEY - do you know how I can filter to see the "16 issues not assigned to sprint"?

Hi @Kevin.Bruce 

Did you try to click on the first link jjust below "View backlog in Jira" 

I think it should be ok with a specific focus on green statused issues.  

Have your Jira project admin check the sprint board as it may have statuses like - descoped or duplicates etc. not being visible when you are looking at the sprint itself.

If you run an issue report for the team where sprint = {your specific sprint} then this might highlight as well where the missing 38 points are.