Sprint Overstated

Kevin.Bruce August 17, 2023

Hi, hoping someone can help with this query.

I have a team which is showing on JIRA Plans as having 118 story points assigned to the sprint. However when I view the sprint the team only has 80 points in the sprint.

 

Does anyone know how I can get the story points on the Plans view to be updated correctly?JIRA Blacklog Sprint.JPGJIRA Plans Sprint Capacity.JPG

2 answers

1 vote
Jean-Emmanuel BANQUEY
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 17, 2023

Hi @Kevin.Bruce 

The 38 points are on the Done issues. 
You should clear the Sprint field and/or fill the Resolution field as Done (not the status) on these issues (only possible during a status transition ! you'll have to modify the transition to Done with a post-action)

Watch out also "16 issues not assigned to sprint" probably means it will not be taken into account when you'll start the sprint.

Hope it'll helps !

Kevin.Bruce August 17, 2023

thanks @Jean-Emmanuel BANQUEY - do you know how I can filter to see the "16 issues not assigned to sprint"?

Jean-Emmanuel BANQUEY
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 18, 2023

Hi @Kevin.Bruce 

Did you try to click on the first link jjust below "View backlog in Jira" 

I think it should be ok with a specific focus on green statused issues.  

0 votes
Simon Carroll August 17, 2023

Have your Jira project admin check the sprint board as it may have statuses like - descoped or duplicates etc. not being visible when you are looking at the sprint itself.

If you run an issue report for the team where sprint = {your specific sprint} then this might highlight as well where the missing 38 points are.