We are currently evaluating if and how to use Portfolio for JIRA for managing Scrum projects with multiple teams. In our exemplary setup, we have 3 different teams, each of them with their own board, and a portfolio plan integrating the 3 projects' boards. All 3 teams are supposed to work in parallel sprints and produce a common product increment.
The scenario I am struggling with is as follows:
In order to use the available capacity ideally, I am shifting a story from Team A's sprint 1 to Team B's sprint 1 in Portfolio. This is correctly displayed in the schedule view. I navigate to Team B's board and start sprint 1. The shifted story from Team A is not visible, only the stories originally assigned to Team B. A warning message explains there is 1 hidden issue in this sprint. Fair enough.
The problem happens in Team A's board. By having started Team B's sprint (that includes a story from Team A's board), there is already an active sprint in Team A's backlog (called Team B's sprint 1). This implies I cannot start the sprint 1 planned for Team A.
All I wanted to do is have A and B work in parallel and B take over a story from A because they have the capacity.
Can anyone help explain what I am doing wrong? Or does the available functionality not support my use case? Please advise.
Thanks & Regards, Nicole