Hello,
In Advanced Roadmaps for scrum teams the Capacity is defaulted to 30 points, and I realize I can change that, but it for all sprint for that team.
I have a PI plan that is built out for 8 teams that consist of 3 - 2 week sprints for each team.
Since I know planned time out of the office for any given sprint I would like to be able to set a Capacity velocity per sprint.
So let's say for Team Green has a base level of 44 points per sprint.
In Sprint 1 - 2 people will be out for planned time off and In Sprint 2 - 3 people will be out for planned time off, but the Capacity can only be set for all sprints.
Is there I way we can set different values for each sprint?
It is possible! On your timeline, select the sprint that you want to edit, then click on the number itself. This allows you to subtract capacity from your team based on individual absences.