Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Setting Future Sprint Dates in Jira board to pull through in advanced roadmaps

Hi,

Another question from me around advanced roadmap utilisation.

I have created a whole bunch of future sprints as I'm trying to get ahead with my planning.  

Is there a way we can set the actual date of future sprints?  One i'm using as an example starts 02/07/2020, however won't be live until we finalise planning tomorrow afternoon.

How can I get my roadmap to pull through the date of this sprint if I can't set a date in Jira for future 'not live' sprints? 

Roadmap defaults date to Sept, have I missed something that I should have done apart from set actual dates on my epics?

Thanks in advance,

Sarah

jira example.png

2 answers

I am facing same issue too, not sure how to set the sprint dates for all future sprints. 

Did you ever get a resolution for this? The same thing has happened to me. 

We have multiple teams/boards using the same sprints, which are in the correct order in the teams backlogs but Advanced Roadmaps is bringing them in out of order.

Suggest an answer