Hi,
Another question from me around advanced roadmap utilisation.
I have created a whole bunch of future sprints as I'm trying to get ahead with my planning.
Is there a way we can set the actual date of future sprints? One i'm using as an example starts 02/07/2020, however won't be live until we finalise planning tomorrow afternoon.
How can I get my roadmap to pull through the date of this sprint if I can't set a date in Jira for future 'not live' sprints?
Roadmap defaults date to Sept, have I missed something that I should have done apart from set actual dates on my epics?
Thanks in advance,
Sarah
I am facing same issue too, not sure how to set the sprint dates for all future sprints.
Did you ever get a resolution for this? The same thing has happened to me.
We have multiple teams/boards using the same sprints, which are in the correct order in the teams backlogs but Advanced Roadmaps is bringing them in out of order.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.