I have recently started playing with Portfolio for jira and am running into some problems with the progress bar. Here are a few details to give some context.
When setting up my plan, I am only filtering for the project (Project = XYZ). No other board filters or status filters are being applied so I should get everything.
On my Portfolio plan, I am filtering for all issues, all statuses, and with a time from of the entire 2018 calendar year.
So when I move an issue to Done on my scrum board, I will go to my Portfolio plan and refresh the page. When I do that, the progress bar updates and shows green, indicating progress to the parent and the release. When I hit the "Calculate" button, the closed issue goes away and my progress bar shows no progress.
Is this supposed to happen? And is there a way I can get the Done items to show so the progress bar can show actual progress?