Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Portfolio parallel tasks

Edited

We have Teams with only one Person, and per Definition is a parallel work not allow.  From time to time Portolio plan and calculate this resouce to a parallel work.  Is this a configration Problem or a known Problem ?

 

BR

Ralf

 

1 answer

1 vote
Earl McCutcheon
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
Aug 09, 2019

Hi Ralf,

Portfolio is going to attempt to schedule as much work as a user can complete based on the scheduling factors input for the user and issues.   Described in more detail at the following links, noting one is for server and one is for cloud, but the two docs describe the same behavior in alternate ways and I recomend checking out both versions as the functionality overlaps between the platforms in this particular article:

To remove the ability for the user to be able to run parallel tasks I would recomend setting up dependencies on the issues so that the next issue cannot be scheduled until the first issue is expected to be completed.  details on setting up dependencies can be seen here:

Regards,
Earl