Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Portfolio indicates there's 1 Uncommitted Change, but there's not

Not entirely sure how/when this happened to my Portfolio plan, but I believe it occurred after adjusting some of my Team Members. After changing some people around (deleted one, changed available hours of another), I ended up with the following condition:

My Plan shows 1 Uncommitted change, even though when I go to commit it, there is nothing changed and and I get the smiley face that I'm all set.

The other condition is now I get the warning that my Plan has exceeded the 5 Year Horizon. When, actually, I don't believe there is anything actually driving it. Maybe there's one story that has some weirdness that's causing this, but I haven't found it yet.

Anyone ever experienced this?

Terrell

 

1 answer

1 accepted

0 votes
Answer accepted
Thomas
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
Jan 10, 2018

Hi @Terrell Teague,

 

For this uncommitted changes: this is a known issue, I'd suggest having a look at https://jira.atlassian.com/browse/JPOSERVER-1527 for status tracking and workarounds.

 

For the schedule hitting the planning horizon: Have a look at the estimated issues and look for an error sign in the scope table, being able to identify which issue is causing this is a good first step. The typical situation is that due to skills or just availabilities work can be started but not finished which pushes Portfolio to look further in the future until hitting the planning horizon.

Hopefully that will help.

 

Cheers,

Thomas

The fix you mentioned for the uncommitted change did the trick, thanks!

Was eventually able to find the story that was causing my schedule to blow up thanks to your input.