Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in

Portfolio-Program not showing Release offtrack for issues scheduled beyond Release dates

Susneha Patil October 29, 2019

Hello all!

 

I have a Query based Plan in 'Portfolio for Jira' which has Epics and stories with scheduled end date beyond the Release date to which they are tagged to.

I built a Program using this Plan. I am expecting the release to have turned Red. But, it's not.

Am I missing something? I want 'Portfolio for Jira' to show releases red when the plan has items beyond the release date. How does it work?

---

Update: 31-Oct-2019

Apparently, the feature available just shows the overbooked releases and not 'offtrack releases'. Couldn't find the Atlassian documentation in this regard though.

1 answer

1 accepted

0 votes
Answer accepted
Lachlan G
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
November 7, 2019

Hey Susneha,

 

Your expectation sounds correct to me. 


Could you create a support ticket at https://getsupport.atlassian.com?
That way we can provide you with support specific to your circumstances and with higher security. 

 

Thanks,

Lachlan

Portfolio for Jira Server Team

Susneha Patil
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 8, 2020
Bruno Mazzoco January 10, 2020

Hi, 

I have same situation.

Didn't understand about the part of only showing "the overbooked releases" . I would expect to see all the releases as in Portfolio Project Plan. 

My expectation was also to have Release Status Off-track (Red) when items schedule as end-date after the Release Date (off-track situation) in this Program View too. 

Also, I was testing putting some issues with Start-Date also after the release date (another situation of off-track) and it seems that this is a JIRA Project BUG too for not indicating as off-track as per the documentation described in here: 

"Off-track - If any of the issues is starting or ending beyond the release date then the release is off-track."

https://community.atlassian.com/t5/Portfolio-for-Jira-questions/How-is-Release-Status-on-track-off-track-calculated/qaq-p/1139636

With many thanks and kind regards,

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events