Overlapping Active Sprints

Dominic O'Connor
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 2, 2018

I'm getting an error from Portfolio that I have multiple overlapping sprints, but when I look at the sprints, they are not actually overlapping. Is this a new bug or something I'm missing?Screen Shot 2018-01-02 at 4.37.30 PM.pngScreen Shot 2018-01-02 at 4.37.49 PM.pngScreen Shot 2018-01-02 at 4.38.05 PM.png

1 answer

1 accepted

1 vote
Answer accepted
Thomas
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
January 2, 2018

Hi @Dominic O'Connor,

 

The most likely issue is that your sprint DEMETER-RS-26 is in the past but is still active (not closed) saying that it is still running. As a result it is in fact overlapping EOS-RS-1.

If that makes sense, I'd advise to complete the DEMETER-RS-26 sprint and then reload / recalculate the plan to see if the error persists.

 

Cheers,

Thomas.

Dominic O'Connor
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 2, 2018

Yeah that seemed to do it. Overlapping was confusing nomenclature since the end date that we defined didn't actually overlap with the next sprint, but conceptually your explanation makes sense. Thanks!