Hi, I would like for the end date of a sprint to determine the due date of an issue. So if I assign a given sprint to an issue, the due date of that issue becomes the end date of the sprint.
The farthest sprint end date of all the issues in an Epic should determine the due date of the Epic and be visualized on my roadmap.
Any tips on how to achieve these things are greatly appreciated!
Thank you
Welcome to the Atlassian Community
For your first paragraph, simply configure the plan as below.
i.e. have Due Date as the end date for the plan and make sure the tickbox is ticked to enable sprint dates when issues don't have dates.
For the 2nd paragraph, you would need to do some form of automation to achieve that.