Are you in the loop? Keep up with the latest by making sure you're subscribed to Community Announcements. Just click Watch and select Articles.

×
Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

JIRA Portfolio - Incorrect timeline for stories within an Initiative

Here is the scenario

- I created an Initiative.

- Created two epics with Initiative

- Created two stories with one of the epic

- Assigned a release with a fixed release date (31-July-18)

- Gave story points to Initiative only

- Clicked 'Calculate'

- As a result, Timeline showed that initiative will be done by 10-July but stories within that will be completed by 31-July.

 

Is it not an incorrect representation? This indicates that there is no relationship between Initiative and Story.

 

1 answer

0 votes
Shannon S
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
Jun 22, 2018

Hi Amit,

Without story points, Portfolio is not able to estimate the work required and thus schedule the item in the plan.

Have a look here:

Therefore, it has moved it to the end by the release date as it would be completed by that date.

I hope that clarifies things. Let us know if you have any follow-up questions.

Regards,
Shannon

Shannon,

i agree that without the story points, stories will be scheduled to last the release date but in this scenario where they are part of an initiative and that initiative is scheduled to end on 10 july, shouldnt that timeline be respected?

 

If not, what is difference between a unestimated story which is part of a scheduled initiative vs a unestimated story which is not part of any initiative?

Shannon S
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
Jun 25, 2018

Hi Amit,

So currently Portfolio works from the bottom-up with the estimations expected on the bottom of the hierarchy tree.

If this behavior isn't working for you then you can change the unestimated items scheduling option in the plan. Have a look at the following:

By choosing not to schedule unestimated items, Portfolio for Jira will ignore any unestimated items in your plan. These items will not have any impact on the schedule as well.

Let me know if you have any questions!

Shannon

I  think your first line answers my question. 