Hi all,
I'm monitoring each team member's scope vs capacity (workload) with a portfolio capacity view.
But I realized the 'capacity' parts here is not affected by daily time progress.
It seems that the capacity used for calculation is based on the Sprint 'Total' capacity not Sprint 'Daily updated' capacity.
For example, lets' assume that my capacity was 160hrs = 8hrs/a day x 4 weeks(20days) when I started a October sprint. After two weeks later, the updated 'capacity' is supposed to be 80hrs (because I only have two weeks left to finish my works assigned to this October sprint) to calculate the exact overload comparing 'Remaining hours'.
Work remaining is reduced daily, but why capacity is still the same as the time to start the sprint?
Is there any way to modify 'capacity' reflecting time progress?
Thank you!
Kind regards,
Jenny