I currently have multiple plans for each large project a subset of developers are working on, and I'd like to link all of the plans together into one master-plan for management to watch the entire company move forward under different plans/ have one place for transparency to see what every team is working on.
Is it possible to link the plans or do I need to create a new plan that contains all underlying epics across all the different plans I created ?
Thanks in advance!
You should create a Program, which is a special type of plan designed specifically for this purpose.
If you want to learn more, check out Atlassian documentation.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Stupid question, but where is the button to create a Program ? Is it a permissions thing ? Or are there multiple versions of Portfolio and we just don't have access ?
For the life of me I can't find how to actually start the creation process.
Thanks so much,
Cheers
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Walter Buggenhout - let me know if you happen to know about the above! Still an issue for us.
Cheers
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
does this help you:
https://confluence.atlassian.com/jiraportfolioserver/creating-and-deleting-programs-931037970.html
Cheers