Are you in the loop? Keep up with the latest by making sure you're subscribed to Community Announcements. Just click Watch and select Articles.

×
Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Is it possible to create a plan over multiple teams using target date instead of calculated end date

While trying to aggregate multiple plans from differnt teams into one programm plan Jira uses a calculated end date and not the target date from the individual plans for each epic. some Initiatives/Epics out of the hierarchy aren't even shown in the aggregated plan. is there a fix to use only the target date for such a plan?

1 answer

0 votes
elizabeth_jones
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Apr 15, 2021

Yes, if you have target start and end, as I do. In the configuration screen you can choose those. Screen Shot 2021-04-15 at 4.52.56 PM.png

 

As an example, I have created a project to house all initiatives. I have a plan that pulls in all initiatives from that project and then displays them on the roadmap by target start and target end dates. Hope this helps :)