The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Is it possible to create a plan over multiple teams using target date instead of calculated end date

Daniel Brenner
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 15, 2021

While trying to aggregate multiple plans from differnt teams into one programm plan Jira uses a calculated end date and not the target date from the individual plans for each epic. some Initiatives/Epics out of the hierarchy aren't even shown in the aggregated plan. is there a fix to use only the target date for such a plan?

1 comment

Comments for this post are closed

Community moderators have prevented the ability to post new comments.

elizabeth_jones
Community Champion
April 15, 2021

Yes, if you have target start and end, as I do. In the configuration screen you can choose those. Screen Shot 2021-04-15 at 4.52.56 PM.png

 

As an example, I have created a project to house all initiatives. I have a plan that pulls in all initiatives from that project and then displays them on the roadmap by target start and target end dates. Hope this helps :)