In a Program Schedule - Epics marked Done disappear.

Michael Glaser
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 28, 2020

Is there an option for them to remain on the view?

3 answers

0 votes
Sherry Xie
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 19, 2021

We also have this problem, is this a bug or expected feature for Advanced Roadmap?

0 votes
Jenn Sherman
Contributor
August 26, 2020

I'm noticing this same behavior in the improved interface for Advanced Roadmaps for Jira.  When an epic's status is changed to Done, that epic disappears from the plan.  Is there a way to keep the epic on the plan until it's been Done for 30 days (per the plan configuration)?

0 votes
Michael Glaser
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 10, 2020

More info:

Scheduled Start and Scheduled End Dates disappear from the Scope tab of a program once the Status (not Epic Status) is set to Done.   This results in the Epic not being being displayed in Schedule tab, even if your select all for Status.   If the Status is set back to In Progress the Dates comes back in the Scope tab and the Epic is displayed in the Schedule.