I am making changes to my team and weekly hours in JIRA Portfolio and my schedule does not change. What am I missing!?
**Using the latest portfolio version
Questions
Hi Natalie,
Dunno if you've found the answer elsewhere yet.
Your questions as I understand it:
You may also want to check your plan settings for the following:
*I think the teams settings on these will override the plans. Although i'm unsure.
Since you haven't mentioned the sprint cadence portfolio will just think you have a less efficient team delivering the same amount of story points. I generally work on an 80% efficiency model so in theory if you went simplistically as 1 story point = 1 day. Each team member you add should = 8 points of cadence and that way your schedule should scale accordingly.
Hopefully helps!
Thanks
Lewis