If I update the query will my portfolio plan change as well?

NAW October 11, 2019

Hello everyone,

 

I am a new portfolio user. We have a release portfolio that multiple teams are currently using from last year. The source is a filter picking from multiple projects

Please let me know if I update the query to include the new project. Will it affect the plan in anyway?

 

Thanks!

 

 

1 answer

0 votes
Earl McCutcheon
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
October 14, 2019

Hello,

Yes, the plan is pulling in the issue sources based on the filter, either applied by a Board linked to the plan or applied as a direct saved filter to the plan, so editing the filter will update the issue present in the plan based on the filter changes.

Regards,
Earl