Hello! I created a Program from a set of four plans. After adding the plans, I was expecting all epics to appear in the 'Schedule' view when set to 'Epic' in the hierarchy. Unfortunately, only one epic is showing despite there being multiple across the four plans. I have experimented with adding various types of start dates and end dates, and also adding a sprint to the epics. What fields are required to ensure an epic appears in the Schedule view of a Program?

2 answers

1 accepted

0 votes
Answer accepted
Hillary Moore February 29, 2024

Adding a 'Target Start' and 'Target End' date to each epic enabled display in Schedule view.

0 votes
Crystelle S
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 29, 2024

Have you checked the setting for how long you show resolved tickets? Keep in mind, Plans isn't reading your statuses but rather looking for whether your Resolution is empty to start the clock on how long something has been resolved (as does the indexing in Jira and many other add-ons).

Hillary Moore February 29, 2024

Thanks, Crystelle. I found that adding a ‘Target Start’ and ‘Target End’ date to each epic enabled display in Schedule view.

Like Crystelle S likes this
Crystelle S
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 29, 2024

nice! you may want to give this a close so that other community members find it easier :) some only search for solved questions

Like Hillary Moore likes this

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events