Using Portfolio Cloud
I would like Portfolio to calculate the Issues in a sprint based on the velocity of the team.
Currently I can see the capacity and if the sprints are overbooked. I can also see in the Board in the Velocity Chart, that the team commitment is higher than the result.
I would like to see a realistic timeline where issues assigned to a sprint based on the capacity and velocity.
Is this supported by Portfolio?
Thanks,
Joerg
Sort of. Try going into the Teams view and click on the number representing Velocity (pts) on the right side. In the popup that appears, click the Past Velocity tab and then click the Use suggested velocity button.
Not sure if it's exactly what you're looking for but it's the closest I can think of.
Hi Steven,
yes, that is exactly what I'm looking for. Unfortunately there is no popup. I worked in a Server environment and I got this popup but in Cloud not. Is there a different functionality?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Time to up your Loom game! The new Loom Essentials Certification is here! Show off your skills, learn pro tips, and get officially recognized. Perfect for taking your video messaging to the next level.
Learn moreOnline forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.