Hi all,
I'm using auto-scheduler to create a high level project schedule, selecting epics only to schedule at this stage.
However i'm running into an issue which i haven't been able to find the cause of; Auto-scheduler keeps assigning my epics to past dates (-2months).
Steps i've taken to address this:
- removed any prescribed dates
- removed any sprints
- set epic one start date to today
no luck with this so far, thanks in advance.
by a short test in my Plan I was not able to reproduce it. Is it sure that for "Target Start" and "Target End" no dates are entered and is it also safe that Jira and the client PC are having the appropriate date set?
Best regards,
Daniel
HI Daniel ,
I've confirmed that the Target start and end fields are empty and the Client PC is the appropriate date. this is on Jira Cloud, so i don't seem to be able to edit the date - but it is correct, i see this by the Advanced roadmap's orange; today marker.
So strange!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Louise Heller Strange, indeed. In case there won't be replies it could make sense to create a request with Atlassian Support, your plan should allow you to create a request.